Fourteen weeks in, the house is weather-tight. Trusses went up Monday, the membrane was down by Thursday, and the electrical rough-in starts next week.
Electrical and plumbing runs before the walls close. Nothing to decide here.
WEEK 16
Windows
Delivery on the 22nd. Four days to fit.
WEEK 17
Kitchen layout
We mark the cabinets on the floor so you can walk it before anything is fixed.
ONE DECISION
Oak or ash for the staircase?
Both are in the budget. Oak is warmer and matches the floor; ash is paler and will read lighter in the hall. Samples are at the office, or we can bring them to site on Friday.